Skip NavigationSan Bernardino Valley College  
Home | Site Index |   
 
   
 
 
 
   
   
Your future starts here.  
 
 
Start Tab
Prospective Students
End Tab
Start Tab
Current Students
End Tab
Start Tab
Online College
End Tab
Start Tab
Instructional Programs
End Tab
Start Tab
Student Services
End Tab
 
Home
Commencement
Apply & Register
Financial Aid
Schedule of All Classes
Library
News & Events
Staff Directory
College Offices
College Facilities
Employment
Athletics Wolverine Logo
Accreditation
Help Desk


Contact Us

Have a suggestion or opinion for our website?
E-mail us
here.


Project Timelines*
This page will keep our campus community and the public updated on the various projects and their respective timelines.

CAPITAL CONSTRUCTION PROJECTS*

(Timelines are site prep through move-in - Completed items are shaded)

NEW BUILDINGS 
  • Maintenance & Operations
  • Custodial Building
  • Media & Communications
  • NorthHall Replacement
  • Chemistry/Physical Science
CONSTRUCTION TIMELINES
  • 05-08 thru 11-08
  • 09-08 thru 03-09
  • 09-08 thru 03-10
  • 11-08 thru 06-10
  • 03-09 thru 06-11

DEMOLITIONS
  • North Hall (north wing)
  • North Hall (remainder of building)
  • Chemistry
  • Physical Science 
CONSTRUCTION TIMELINES
  • 03-09 thru 09-09
  • 02-11 thru 04-11
  • 02-11 thru 04-11
  • 02-11 thru 04-11 

OTHER RELATED PROJECTS*

(Timelines are site prep through move-in - Completed items are shaded)

PROJECTS
  • Temporary Classrooms/Offices
  • Renovations (KVCR Radio & Refrig) 
CONSTRUCTION TIMELINES
  • 08-08 thru 11-08
  • 10-08 thru 11-08

* Please keep in mind that these construction timelines are estimates and subject to frequent revisions. Timelines have been presented to the College by Kitchell/BRJ Construction Company, our partner in these construction projects.